From the install day back
Design, proof, production and a weather buffer for outdoor pieces, counted back from the install day on working days.

Working daysMonday to Saturday
The stages
Design takes 2 working days when a piece needs it, the proof to approve 1 working day, production 4 working days, and outdoor pieces get a weather buffer of 1 working day. Working days are Monday to Saturday, without public holidays. The installation date can be chosen up to 120 days ahead.
These are proposed lengths for Creaciones Macadeho to confirm.
| Stage | When | Length |
|---|---|---|
| Proof to approve | Tue 20 Oct | 1 working day |
| Production | Wed 21 Oct – Sat 24 Oct | 4 working days |
| Weather buffer | Mon 26 Oct | 1 working day |
| Installation | Tue 27 Oct | on site |