Plan a sign

Schedule

From the install day back

Design, proof, production and a weather buffer for outdoor pieces, counted back from the install day on working days.

A paper calendar on a desk
Working daysMonday to Saturday

The stages

Design takes 2 working days when a piece needs it, the proof to approve 1 working day, production 4 working days, and outdoor pieces get a weather buffer of 1 working day. Working days are Monday to Saturday, without public holidays. The installation date can be chosen up to 120 days ahead.

These are proposed lengths for Creaciones Macadeho to confirm.

Installing on Tuesday 27 October 2026, planned on Saturday 10 October 2026
StageWhenLength
Proof to approveTue 20 Oct1 working day
ProductionWed 21 Oct – Sat 24 Oct4 working days
Weather bufferMon 26 Oct1 working day
InstallationTue 27 Octon site